SWMS Example: Hazards and Control Measures by Trade

Last reviewed November 2026

An example is the fastest way to see whether your own SWMS is specific enough. Below are the kinds of hazard and control rows that hold up when a principal contractor or a regulator reads them: one hazard per row, the control naming what is physically in place, and a residual risk that shows the control does something.

What a good row looks like

Take one line from an electrical job:

Hazard Risk before Control measure Residual
Live conductors in the switchboard being worked on High Isolate the supply, lock out and tag, and test for dead with a proving unit before work starts Low

Three things make that row work. The hazard names the actual energy source rather than "electrical hazard". The control is a sequence someone can check. And the residual risk drops because of a specific action, not because the worker promises to be careful.

The same hazard written as "electrical hazard - ensure caution" would fail the same review.

Electrical

Hazard Risk before Control measure Residual
Live conductors in the board being worked on High Isolate, lock out and tag, test for dead with a proving unit Low
Reaching ceiling services at height Medium Podium step with rails on level ground; ladder tied off and footed for short access Low

Plumbing

Hazard Risk before Control measure Residual
Entering a pit, tank or roof space High Atmosphere tested first, gas monitor worn, standby person outside with a rescue plan Medium
Brazing near flammable material High Fire blanket and extinguisher on hand, 10 m clearance, area watched for 30 minutes after Low

Carpentry

Hazard Risk before Control measure Residual
Circular saw and nail gun use High Guards fitted, push stick for narrow cuts, hearing and eye protection, gun never pointed at anyone Medium
Working at height on framing or scaffold High Guard rails and toe boards, harness to an anchor point, scaffold tagged and inspected Medium

Concreting

Hazard Risk before Control measure Residual
Wet concrete on skin and eyes Medium Waterproof gloves and boots, long sleeves, wash station on site Low
Concrete pump boom over the work area High Exclusion zone under the boom, spotter in radio contact with the pump operator Medium

Roofing

Hazard Risk before Control measure Residual
Falling from the roof edge or a penetration High Perimeter rail or safety mesh, penetration covers fixed, harness and anchor point Medium
Heat, sun and fatigue on the roof Medium Early start, water and shade on the roof, crews rotated, UV protection Low

Excavation

Hazard Risk before Control measure Residual
Trench collapse on a person inside it High Batter or shore the trench, spoil back 1 m from the edge, daily inspection by a competent person Medium
Striking underground services High Dial Before You Dig plans on site, hand expose within 1 m, spotter beside the operator Medium

Filling the rest of the form

The hazard rows are the middle of the document, not the whole thing. Before them sit the company details, the ABN, the principal contractor, the site address and the activity. After them come the consultation record and the signatures. A row set that is perfect but attached to a document that does not name the site is still going to come back.

Two habits make the difference. Write the hazard in the words the crew uses, not in regulator language. And name the person or the check, not just the control: "checked by the supervisor before first ascent" beats "harness to be used".

Turn one of these into your own

The free SWMS builder loads the starting rows for six trades — electrical, plumbing, carpentry, concreting, roofing and excavation — and lets you edit every one, add your own, sign on the phone and export an A4 PDF. If you want the surrounding rules first, read what a SWMS has to contain.

Common questions

How many hazards should a SWMS list?

Two to eight rows is typical for a single activity. The number matters less than whether each hazard on the site is covered by a row, and whether every row has a control that is actually in place.

Do I need a risk rating for each row?

A risk matrix is not mandatory in the document itself, but most principal contractors expect a before and after rating. The value is in showing that the control reduces the risk, not in the numbers themselves.

What happens if the site changes after it was signed?

Edit the rows, re-sign and keep the superseded version. The signed document should always match the controls that are actually in place on site.